The order, and why it is fixed
A new slab-on-grade house goes up in a sequence that is set by physics and by the building code: you cannot frame before the slab, cannot insulate before the pipes and wires are in, and cannot hang drywall before the inspector has seen what it will cover. In outline:
The same order is grouped into four broad phases of construction, which is how builders and lenders usually talk about progress.
- Site and foundation: survey and staking, termite pretreatment, under-slab plumbing, the pre-pour inspection, the pour, and on a post-tensioned slab, stressing.
- Structure and shell: framing and bracing, roof dry-in, windows and weather barrier, then cladding such as brick veneer.
- Systems: plumbing top-out, electrical rough-in and HVAC rough-in, followed by the framing inspection, then insulation and air sealing.
- Completion: drywall and interior finishes, energy testing, final grading, the final inspection, and the builder walk-through.
Real schedules overlap. Exterior finishes often proceed while interior rough-ins are underway, and landscaping can start before the final. But the dependencies do not change, and the dependencies are what matter for inspection.
The sequence is a series of cover-ups
Each stage hides the one before it. The pour hides everything below the slab. Cladding hides the house wrap and window flashing. The roof covering hides the underlayment. Drywall hides framing, fireblocking, pipes, wires, ducts and wall insulation all at once. The cover-up point explains why that changes the cost of a defect so sharply, and which records stand in for what can no longer be seen.
That is why the most useful checklist is organized by time rather than by room. The new construction inspection checklist groups what to look at and which document to request around the three windows that matter most: before the pour, before drywall, and before closing.
How long the windows are
Census Bureau data, as analyzed by the National Association of Home Builders (NAHB), put the average new single-family house at 8.8 months from permit to completion in 2025, with 7.4 of those months under construction. NAHB's November 2026 builder survey placed site work and foundations at a little over two weeks, framing and rough-ins at about 3.7 weeks each, and interior finishes at 6.4 weeks, the longest stage. The inspection windows inside those stages are measured in days. See how long each construction stage takes.
What each stage leaves on paper
Some stages leave strong documents: the form survey, the foundation inspection or engineer's letter, the termite certificate, the elongation record, the rough-in and framing results, the energy certificate, the certificate of occupancy. Others leave almost nothing: the roof underlayment, the window flashing and the brick ties typically have no dedicated record. The stage pages each list what the stage leaves behind, under "Paper it leaves" or in the facts panel.
A note on the answer pill
Each stage page opens with a colored pill answering one question: once the house is finished, can this work still be checked? Still checkable after move-in means it can be seen or measured later. Partly hidden after completion means some of it remains visible. Hidden once the next stage starts means the next layer covers it for good, and the documents are the only evidence. Most of the expensive stages fall in the third group.
How to use this section
Read the cover-up point first, for the idea. Use the checklist during construction. Use how long each stage takes to anticipate the windows. Then follow any stage from the list above for the detail.
Where the numbers come from
Construction times are from NAHB's analyses of Census data for 2025 and its 2026 builder survey. The required inspection order is in IRC adoptions such as Albany, Georgia's.