Post-Tension Slab Stressing

The steel cables in the slab are stretched after the concrete cures, and a one-page record shows whether each one reached its design length.

What stressing establishes

Stressing establishes that the steel cables cast into a post-tensioned slab were stretched to the force the engineer designed, as measured by how far each one elongated. A post-tensioned slab uses a grid of high-strength steel cables, called tendons, encased in plastic sheathing and laid through the slab before the pour. Days later, after the concrete gains strength, a crew pulls each tendon with a hydraulic jack and locks it off at the slab edge. The tensioned cables squeeze the slab, which makes it stiffer and more resistant to cracking on shifting clay soils. Post-tensioned slabs are common across Texas and the Southwest for exactly that reason.

The proof that the squeezing happened as designed is not visible in the finished house. It is in a sheet of numbers called the elongation record.

How the stressing is done and measured

Before stressing, the crew marks each tendon tail at the slab edge, often with spray paint. The jack pulls the tendon, the wedges seat in the anchor, and the crew measures how far the mark moved. That distance is the measured elongation. The engineer has already calculated what each tendon's elongation should be, given its length and the force required. Comparing the two is the check.

Concrete Network describes the typical sequence: once the concrete reaches about 2,000 psi, which usually happens within the 3 to 10 days the Post-Tensioning Institute recommends, the tendons are stressed. As STRUCTURE magazine puts it, the elongation record is "the primary tool for the engineer and owner" to confirm the permitted drawings were followed. Measured elongations are commonly accepted within about plus or minus 7 percent of the calculated value under ACI 318.

The rule about cutting the tails

After stressing, the excess cable beyond the anchor, the tail, is cut off, the anchor is capped and the pocket at the slab edge is filled with grout. Good practice holds those tails until the engineer approves the record. If an elongation is out of tolerance, the crew may have to restress, which is far easier while the tail is still there. Once tails are cut and pockets grouted, the slab edge looks like any other, and the stressing history is entirely on paper.

What the record does not establish

The record proves force at the moment of stressing. It does not prove the tendons were placed at the correct height and spacing before the pour; that is the pre-pour inspection. It does not prove the concrete was strong enough, though stressing too early is a known cause of anchor failures. And it does not predict how the slab will behave over the years, which depends heavily on soil moisture. The Post-Tensioning Institute stresses that long-term performance of a slab on ground depends on good drainage and on moisture maintenance by the owner.

The warning every owner needs

Never cut, core or drill into a post-tensioned slab without the engineer's direction. A tendon under tension carries tens of thousands of pounds of force. Cutting one can release it violently, and a cut tendon is difficult and expensive to repair. Many builders stamp a warning into the garage slab or the slab edge for this reason. Ordinary projects trigger it: a new floor drain, a toilet relocation, anchoring a safe, or fastening a wall track with a powder-actuated nail deep enough to reach a cable.

Common mistakes

Stressing late, after the slab has already cracked from shrinkage, defeats part of the purpose. Losing the record is the second; it should go into the closing binder described in documents to collect at closing. The third is landscaping and drainage that soak one side of the slab and leave the other dry, which the final grading stage is meant to prevent.

Where the rules come from

The stressing sequence and the 3-to-10-day window are summarized by Concrete Network. The role of the elongation record and the hold on cutting tails are explained in STRUCTURE magazine's best practices for post-tensioning elongation records. The owner's drainage and moisture responsibility is in the Post-Tensioning Institute's construction and maintenance presentation.

Frequently Asked Questions

How do I know if my house has a post-tensioned slab?

Look for a stamped warning in the garage slab or for grouted anchor pockets along the slab edge, and ask the builder for the foundation plans and the elongation record.

When are post-tension cables stressed?

After the concrete gains enough strength, commonly within about 3 to 10 days of the pour. The engineer's specifications set the required strength.

What is an elongation record?

A sheet listing each tendon's measured stretch during stressing next to the calculated value. The engineer reviews it to confirm the slab was stressed as designed.

Can I drill into a post-tensioned slab?

Not without the engineer's direction and a method to locate the tendons first. Cutting a tensioned cable is dangerous and costly to repair.

Does a passed stressing record mean the foundation will never move?

No. It confirms construction matched the design. Long-term movement depends largely on soil moisture and drainage around the house.