Overview
This directory lists all seventeen stages of building a typical slab-on-grade house covered on this site, each with its answer stated before anything else: whether that work is still checkable after move-in, partly hidden once the house is finished, or hidden for good as soon as the next stage starts. Use the table if you already know which stage you are asking about; browse by phase below if you do not.
The answer in the table is the reason the site exists. A buyer standing in a finished house can measure the slope of the yard, run every faucet, read the label on the electrical panel and retest the house's air tightness. That buyer cannot see the drain lines under the slab, the termite treatment in the soil, the cables in a post-tensioned foundation, the flashing behind the brick, or the insulation inside the walls. For the hidden stages, what survives is a record: a passed inspection in the permit file, an engineer's letter, a certificate from a pest control company, a stressing record, a tested energy certificate at the panel. Knowing which stages fall into which group tells a buyer where to look during construction, and which documents to ask for before closing.
How the stages are grouped
The stages are grouped two ways. By phase, they follow the order the house goes up: site and foundation, structure and shell, systems rough-in, and completion. That order is fixed by physics and by the building code, which places its inspections immediately before each cover-up point. By kind of evidence, they split into stages a code inspection checks and stages proven only by a document. The second split matters because a code inspection, valuable as it is, is a check against minimum requirements at a single moment, while several of the most consequential stages, such as the window flashing and the brick veneer ties, have no dedicated inspection in most jurisdictions at all.
What each stage page covers
Every stage page follows the same pattern: what the stage establishes, how it is done, who checks it and under which code section, what it does not establish, what can still be seen afterward, the common mistakes, and where the rules come from, with links to the city handouts, statutes and code commentary the page was written from. A short facts panel on each page states the stage's key numbers and the paper it leaves behind.
The pages describe common practice and the model code as adopted in named jurisdictions, with Texas examples where Texas rules differ. Local codes vary, and the edition in force when a house was permitted is the one that applied to it; the guide to code editions and local amendments explains how to find it.
Not every new house passes through every stage listed here. A house on a conventionally reinforced slab has no post-tension stressing; a house with siding has no brick veneer; a house outside city limits in Texas may have no certificate of occupancy. The pages say where a stage applies.
| Stage | After move-in | Phase |
|---|---|---|
| Form Board Survey and Staking | Partly hidden after completion | Site and foundation |
| Termite Pretreatment | Hidden once the next stage starts | Site and foundation |
| Under-Slab Plumbing and the Water Test | Hidden once the next stage starts | Site and foundation |
| The Foundation Pre-Pour Inspection | Hidden once the next stage starts | Site and foundation |
| Post-Tension Slab Stressing | Hidden once the next stage starts | Site and foundation |
| The Framing Inspection and Wall Bracing | Partly hidden after completion | Structure and shell |
| Roof Dry-In: Underlayment and Flashing | Hidden once the next stage starts | Structure and shell |
| Windows, Flashing and Weather Barrier | Hidden once the next stage starts | Structure and shell |
| Brick Veneer: Weep Holes, Ties and Air Space | Partly hidden after completion | Structure and shell |
| Plumbing Top-Out and the Gas Line Test | Hidden once the next stage starts | Systems rough-in |
| The Electrical Rough-In Inspection | Partly hidden after completion | Systems rough-in |
| HVAC Rough-In and Equipment Sizing | Partly hidden after completion | Systems rough-in |
| Insulation and Air Sealing Before Drywall | Partly hidden after completion | Systems rough-in |
| Blower Door and Duct Leakage Testing | Still checkable after move-in | Systems rough-in |
| Final Grading and Drainage | Still checkable after move-in | Completion |
| The Final Inspection and Certificate of Occupancy | Still checkable after move-in | Completion |
| The Builder Walk-Through and Punch List | Still checkable after move-in | Completion |