What top-out establishes
Top-out is the plumbing trade's name for the rough plumbing installed above the slab, inside walls and ceilings: the drain and vent pipes rising to the roof, the hot and cold supply lines to each fixture location, and usually the gas piping. The top-out inspection establishes that this piping was installed and tested tight before it was concealed. Many Texas and western jurisdictions list it as a distinct inspection; Kingsville, Texas, for example, sequences plumbing as underground, sewer connection, water line, top out and final, with gas as underground, rough-in and final.
It follows the under-slab test and comes before insulation and drywall, at the same stage as the electrical and mechanical rough-ins.
How the piping is tested
Under the International Residential Code (IRC) and the plumbing code it draws on, drain, waste and vent (DWV) piping is tested with water to a head above the highest fitting, 10 feet under the 2021 IRC, or, for piping other than plastic, with air at 5 pounds per square inch, held for 15 minutes. Water supply piping is tested at not less than its working pressure with water or, for piping other than plastic, with air at 50 psi, again for 15 minutes. The inspector reads the gauge or the standpipe and looks for leaks at the exposed joints.
Gas piping is tested separately on the rough system. The IRC's fuel gas rules require a pressure test before the piping is concealed or appliances connected; the test pressure and duration depend on the edition and local amendments, so the number belongs to the local code rather than to a universal rule.
Two details inspectors look for
CSST bonding. Corrugated stainless steel tubing (CSST), the flexible yellow-jacketed gas line common in new houses, must be bonded to the electrical grounding system as required by the code and the manufacturer, because lightning-induced current can perforate unbonded tubing. Austin's top-out checklist lists the bonding requirement explicitly.
Protection plates. Where a pipe passes through a stud or joist close to the edge, a steel plate protects it from drywall screws and nails. A missing plate is invisible until a picture hanger or a trim nail punctures a supply line inside a finished wall.
What the inspection does not establish
It does not establish water pressure or flow at the fixtures, which depend on the service and the regulator. It does not establish that drains slope correctly everywhere, though gross problems are visible. And it does not check fixtures, valves or the water heater installation, which come at the final.
What remains visible
After completion, the fixtures, shutoff valves, the water heater and its relief valve discharge, the gas meter and the visible gas connections remain. Everything in the walls is hidden. The early warning signs of a concealed problem are a running water meter with every fixture off, unexplained stains on ceilings below bathrooms, or a smell of gas near an appliance connection.
The parts a buyer should locate before move-in
Three plumbing components deserve a few minutes during the walk-through because they matter in an emergency. The main water shutoff, at the meter box or where the line enters the house, stops all water to the house. Each fixture has its own stop valves under sinks and behind toilets. And the water heater's temperature and pressure relief valve has a discharge pipe that should run to an approved location, not end in the attic or a closet; the code sets where it may terminate.
The gas side has a matching set: the shutoff at the meter, and an appliance shutoff valve near each gas appliance. Knowing where these are, and confirming they turn, is worth more in a leak than anything else on this page.
Common mistakes
Missing protection plates, drains and vents cut into framing members beyond allowable limits (a structural problem picked up at the framing inspection), unbonded CSST, test gauges reading pressure that was never actually applied, and debris in drain lines are the recurring list. The last is cheap to catch: a camera run through the drain lines at the end of construction.
Where the rules come from
The test pressures and 15-minute hold are summarized in residential plumbing study material such as this IRC testing summary and in inspection checklists like Cave Creek, Arizona's rough plumbing list. Austin's top-out checklist covers CSST bonding.