What the framing inspection establishes
The framing inspection establishes that the house's structural skeleton, the walls, floors and roof framing and the connections between them, was built to the approved plans and the building code before insulation and drywall covered it. Under Section R109.1.4 of the International Residential Code (IRC), it is made after the roof, framing, firestopping, draftstopping and bracing are in place, and after the plumbing, mechanical and electrical rough inspections are approved. InterNACHI describes it as usually the last opportunity for the code inspector to see the items about to be concealed. That makes it, along with the rough-in inspections, the pivot of the whole build.
The order matters
The code's sequence is deliberate. Plumbers, electricians and HVAC installers drill and notch the framing to run their lines. Framing inspected before the trades arrive would miss the damage they do. So the framing inspection follows the rough-ins, and inspectors look specifically for studs and joists cut too deeply to carry their load. A joist notched at mid-span or a top plate cut through for a vent pipe without a steel strap is a structural defect introduced by another trade.
Some jurisdictions go further. Topeka, Kansas, requires the wall bracing to be inspected and approved before the electrical, mechanical and plumbing rough-ins begin, and requires the approved bracing plan to be on site.
Wall bracing, defined
Wall bracing is what stops a house from racking sideways like a parallelogram under wind or seismic load. In most new houses it is achieved with structural sheathing, typically oriented strand board (OSB) or plywood nailed to the exterior studs in a specified pattern. The IRC's bracing rules, in Section R602.10, set how much braced wall is needed, where, and how it is fastened. Nail spacing at the panel edges matters as much as the panels themselves, which is why an inspector may look closely at the fastening.
Fireblocking and draftstopping
Fireblocking is material, often lumber or approved sealant, that closes concealed openings so fire cannot travel quickly through hidden spaces such as wall cavities, soffits and the gaps around chimneys and pipes. Draftstopping divides large concealed floor and attic spaces. Both are required by the code and both are invisible once drywall goes up, which is why the framing inspection waits for them.
What the inspection does not establish
It does not establish workmanship that meets no code requirement, such as how straight the walls are or whether the floor is flat enough for tile. It does not establish lumber moisture content. It is also a sampling exercise: an inspector reviewing a house in a fraction of an hour cannot check every nail. Production builders often supplement it with their own quality walk, and some buyers engage a private inspector at this stage. In Texas, the three-stage requirement for new houses outside city limits places the framing and mechanical stage before drywall as one of the three; see new construction outside city limits.
What remains visible
After completion, attic framing, including rafters or trusses, and garage framing are usually still visible. Wall framing is hidden. Problems in hidden framing show up indirectly: cracked drywall at corners, doors that will not latch, or nail pops along a line. Some settling cracks in a new house are normal as lumber dries; diagonal cracks that grow, or doors that begin binding in the first year, are worth reporting before a builder's warranty period ends.
Common mistakes
Overdrilled studs and notched joists, missing hurricane ties or connectors where the plan calls for them, missing fireblocking around penetrations, and trusses altered in the field without an engineer's revision are the recurring findings. The last is worth emphasizing: a roof truss is an engineered component, and cutting a web to make room for an attic air handler changes the design.
Where the rules come from
The order of the framing inspection is stated in model-code adoptions such as Albany, Georgia's, and InterNACHI explains the full sequence in understanding types of code inspections. Topeka's early bracing inspection is in its municipal code.