A code inspector checks a new house against minimum safety rules at a handful of moments, which is valuable and narrower than most buyers assume.

The short answer

A city building inspector checks that a new house meets the minimum requirements of the adopted building code at a few defined stages: the foundation before concrete, the plumbing, mechanical, gas and electrical rough-ins before they are covered, the framing, and the finished house. The focus is life safety, structural adequacy, fire protection, sanitation and, where enforced, energy. The inspector does not evaluate workmanship that meets no code requirement, does not warrant the house, and does not see every part of it.

The inspections the model code lists

Section R109 of the International Residential Code (IRC) names the inspections the building official makes. In the 2015 through 2021 editions they are the foundation inspection; the plumbing, mechanical, gas and electrical rough-in inspection; the floodplain inspection where applicable; the frame and masonry inspection; other inspections the official requires; and the final. Local adoptions add and rename. Groton, Connecticut's list, for example, separates footing, foundation wall, slab, underground utilities, each trade's rough-in, framing, masonry, insulation, fire-resistance-rated construction and final. Kingsville, Texas, lists separate energy, electrical, plumbing and fuel gas sequences, including a plumbing top-out and an energy final for duct and blower door tests.

The order is fixed by what each inspection needs to see. Rough-ins come before covering; the framing inspection follows the rough-ins so it can catch framing damaged by the trades; the final waits for everything else.

What "minimum" means in practice

The building code is a floor. It is written to protect occupants from collapse, fire, electrocution, contamination and similar hazards, and it says so in its purpose. A house can meet every code requirement and still have doors that rub, uneven drywall, a poorly balanced air conditioning system or a window that leaks in a wind-driven storm because of a flashing detail no inspection looks at. Those are quality and workmanship questions, governed by the contract and the builder's warranty rather than the code.

It also helps to understand the inspector's working conditions. A municipal inspector visits many sites a day and spends a limited time at each, with priority on items that affect safety. Inspection is a sample, not a census: an inspector checks representative connections, not every nail.

Where inspections are delegated

Not every city performs every inspection itself. Austin's residential foundation checklist states that city inspectors will not perform foundation inspections for new construction; the design engineer's documentation is relied on instead. Some jurisdictions accept third-party inspection agencies for some stages. In unincorporated Texas, the builder arranges the required inspections from a list of permitted inspectors; see new construction outside city limits.

Some items are rarely or never inspected by the city at all. Prince William County, Virginia, notes that brick veneer ties are not visible at any other required inspection and are only spot-checked. Window flashing, house wrap and roof underlayment typically have no dedicated inspection in most jurisdictions. These are the gaps described on the brick veneer, windows and weather barrier and roof dry-in pages.

What a passed inspection record tells a buyer

The permit record tells a buyer which inspections were requested, passed, failed and re-inspected, and when. That is genuinely useful. A pattern of failed and repeated inspections at one stage tells you where the builder struggled. A final passed without a recorded energy test, in a jurisdiction that requires one, is worth asking about. The record does not tell you what the inspector did not look at, and it does not say the house is defect-free.

How private inspections fit

A private inspector engaged by a buyer works for the buyer, not the city. The inspection has no legal effect on the permit, but it can cover workmanship and hidden-stage details the code inspection skips, at moments the buyer chooses, typically before the slab is poured, before drywall and before closing. In Texas, home inspectors are licensed by the Texas Real Estate Commission (TREC), and TREC-licensed professional inspectors also appear on the list of permitted inspectors for new houses outside city limits.

Where the rules come from

The model inspection list appears in local adoptions such as Groton, Connecticut's required inspections and Kingsville, Texas's list. InterNACHI walks through the sequence in understanding types of code inspections.

Frequently Asked Questions

Does a city inspector check the quality of a new house?

Only against minimum code requirements. Workmanship and quality items that meet no code rule are governed by the contract and the builder warranty.

How many inspections does a new house get?

It depends on the jurisdiction. The model code lists foundation, rough-ins, framing and final, plus floodplain and others where required. Cities often split these into more separate visits.

Can I see the inspection history of a new house?

Usually yes. Building permit records, including inspection results and dates, are public in most cities and are often searchable online by address.

Is a private inspection still useful on a new house?

It covers different ground. A private inspector can examine workmanship and hidden details at stages the buyer chooses, which the code inspection is not designed to do.