Roof Dry-In: Underlayment and Flashing

The roof is covered and sealed against weather before anything inside can proceed, and the layers that matter most end up under the shingles.

What dry-in establishes

Dry-in is the point at which a new house is closed to rain: the roof deck is covered with underlayment and flashing, and usually the windows and exterior doors are set and the walls wrapped. It establishes that the interior can now be worked on without weather damage. It does not, on its own, establish that the roof will shed water for decades. That depends on details installed during dry-in and then covered by the shingles, tile or metal on top.

Builders track dry-in as a schedule milestone. For a buyer it is a quality milestone, because the roofing details that cause most leaks are visible only at this stage.

The layers, from the deck up

The sheathing is the structural deck, usually oriented strand board (OSB) or plywood nailed to the rafters or trusses. Its nailing is part of the framing work. Over it goes the underlayment, a felt or synthetic sheet that is the roof's secondary water barrier; Section R905 of the International Residential Code (IRC) sets underlayment requirements for each type of roof covering. At the eaves and rakes, a metal drip edge directs water off the deck edge and into the gutter or away from the fascia. Where a roof meets a wall, a chimney or another roof plane, flashing carries water across the joint. Around each vent pipe and exhaust, a boot or collar seals the penetration.

In colder climate zones the code also calls for an ice barrier at the eaves. In most of Texas that requirement does not apply, which makes careful flashing even more central to how the roof performs in heavy rain.

Who looks at it

In most jurisdictions there is no separate city inspection of the underlayment or flashing on a house. The roof framing is reviewed at the framing inspection, and the finished roof may be glanced at from the ground at final. The details in between, the valley lining, the step flashing at each course along a sidewall, the kick-out at the bottom of a roof-to-wall joint, are largely the roofing contractor's responsibility and the builder's quality control.

That gap is why roof leaks are among the most common first-year complaints on new houses. A kick-out flashing, the small diverter where a roof edge dies into a wall, is a classic example: if it is missing, water runs down the wall behind the siding or brick instead of into the gutter, and the damage appears months later inside the wall.

What the finished roof hides

Once the roof covering is installed, the underlayment, most of the drip edge and nearly all step flashing are hidden. A later inspection from the roof surface can see the finished covering, the exposed flashing and the penetrations, but not the laps and fasteners underneath. Problems are diagnosed from their effects: stains on ceilings, wet sheathing seen from the attic, rot at the bottom of a wall.

What survives on paper

Shingle manufacturers publish installation instructions, and their warranties often depend on following them, including the number and placement of nails and the use of matching accessory products. Ask the builder which roofing product was installed, whether the warranty was registered, and in whose name. A roof warranty registered to the builder may require action to transfer.

Common mistakes

Missing kick-out flashing, short or overlapping step flashing, underlayment cut short of the eaves, exposed fasteners at the ridge, and vent boots sealed with caulk alone rather than properly lapped are the recurring defects. Nailing that is too high on the shingle, a detail a buyer will never see, can reduce wind resistance and void a warranty. The attic is the best place to look for early signs: daylight around penetrations, wet sheathing, or staining on the underside of the deck after a storm.

Where the rules come from

The International Code Council's technical note on rain and groundwater management explains how drainage layers and flashing work together on walls and roofs. The roof covering rules themselves are in Chapter 9 of the IRC as adopted by the local jurisdiction.

Frequently Asked Questions

What does dried in mean on a new house?

That the roof is covered with underlayment and flashing, and usually the windows and doors are installed and the walls wrapped, so the interior is protected from rain.

Does the city inspect the roof underlayment?

Usually not as a separate inspection. Roof framing is seen at the framing inspection, and underlayment and flashing are left largely to the roofer and the builder.

What is a kick-out flashing?

A small diverter at the bottom of a roof-to-wall joint that sends water into the gutter instead of down the wall behind the cladding. Missing kick-outs are a common source of hidden wall damage.

How can a roof problem be found after the shingles are on?

From the attic, by looking for wet or stained sheathing and daylight around penetrations, and from the surface, by examining exposed flashing and penetrations. Underlying layers can only be inferred.