New Build Checkpoints logo — a house frame with a checkmark at its peakNew Build CheckpointsWhat gets checked as a new house goes up
Category two

Stages proven by a document, not an inspection

These are the stages that pass with no code inspection aimed at them, or whose real evidence is a document produced by someone other than the building inspector. A land surveyor signs the form board survey. A licensed pest control company certifies the termite treatment. A stressing crew records each post-tension cable's elongation for the engineer to review. An energy rater reports the blower door and duct leakage results on a certificate posted at the electrical panel. The builder's representative and the buyer sign the punch list. And for the roof underlayment, the window flashing and the brick veneer ties, in most jurisdictions there is no dedicated inspection at all, which is why those details are behind so many first-year water complaints.

Overview

Why the documents matter

For most of these stages the document is the only evidence that will ever exist. The termite treatment is under the slab. The post-tension cables are stressed, their tails cut and their pockets grouted. The flashing is behind the brick. A buyer who closes without these records has no way to recover what they would have said. The guide to documents to collect at closing lists each one, what it proves, and where to get it.

Reading a document for what it proves

A document proves what it records and nothing more. A termite certificate proves a treatment was applied on a date, not that it survived later trenching. An elongation record proves the cables were stressed as designed, not that drainage around the slab will be maintained. An energy certificate is the exception that proves the rule: the blower door and duct tests it reports can be repeated at any time, which is why the energy stage is the one document-proven stage still fully checkable after move-in.

Several of these stages are also where a buyer's own attention helps most. The flashing and the brick can be seen for a few days before they are covered, and the walk-through is only as good as the list that comes out of it.

Who produces each document

Each document in this category has a different author, and the author decides its weight. A form board survey carries the seal of a licensed land surveyor, which in Texas means a registered professional land surveyor. A termite treatment certificate is issued by a licensed structural pest control business under state rules. An elongation record is produced by the stressing crew and reviewed by the slab's design engineer. An energy certificate is completed by the builder or a registered design professional, and its test results come from the rater who ran the fans. A punch list is a contract document signed by the builder's representative and the buyer. Knowing who signed a document tells a buyer who can answer questions about it later, and who is accountable if it is wrong.

The stages with no document at all

Three stages in this category usually leave nothing a buyer can obtain: the roof underlayment and flashing, the house wrap and window flashing, and the brick veneer ties and air space. Manufacturer installation instructions and warranty registrations are the closest thing to a record, which is why it is worth asking which roofing and window products were installed and in whose name their warranties were registered. For these stages, the only evidence is what someone saw before the cladding went on, which makes them the strongest argument for an independent look between dry-in and cladding.

Keeping the documents together

Documented stages only help if the documents survive. Ask the builder or title company for copies before closing rather than after, because a builder's file on a finished house is rarely kept in one place. Store the survey, the treatment certificate, the elongation record, the energy certificate and the signed punch list with the deed and the warranty booklet. The guide to documents to collect at closing lists them in one place.

If a document cannot be produced, ask the builder to say so in writing. A written statement that no elongation record or energy certificate exists is itself a record, and it is far more useful in a later warranty conversation than a verbal assurance that the work was done.

Whether each construction stage can still be checked after move-in, and which phase it belongs to
StageAfter move-inPhase
Form Board Survey and StakingPartly hidden after completionSite and foundation
Termite PretreatmentHidden once the next stage startsSite and foundation
Post-Tension Slab StressingHidden once the next stage startsSite and foundation
Roof Dry-In: Underlayment and FlashingHidden once the next stage startsStructure and shell
Windows, Flashing and Weather BarrierHidden once the next stage startsStructure and shell
Brick Veneer: Weep Holes, Ties and Air SpacePartly hidden after completionStructure and shell
Blower Door and Duct Leakage TestingStill checkable after move-inSystems rough-in
The Builder Walk-Through and Punch ListStill checkable after move-inCompletion
All 8

Document-proven stages, by phase