The wiring is inspected as a bare skeleton of boxes and cables, the only time anyone sees how it is run and protected.

What the rough-in establishes

The electrical rough-in inspection establishes that the house's wiring was installed in the walls and ceilings in a safe, code-compliant arrangement before it was covered. At this stage the house shows only boxes, cables and the empty panel. The inspector checks how cables are routed, supported and protected, that boxes are the right size for the conductors they hold, and that grounding and bonding paths are in place. Under Section R109.1.2 of the International Residential Code (IRC), rough inspections of electrical, plumbing, mechanical and gas systems are made before covering or concealment and before the framing inspection.

Electrical work in most jurisdictions follows the National Electrical Code (NEC) as locally adopted. The IRC also contains electrical chapters derived from the NEC.

Where it sits in the sequence

Electrical permits on a new house typically produce several inspections. Kingsville, Texas, lists them as temporary power, underground, electrical rough, meter loop (permanent power) and electrical final. The grounding electrode in the footing, often called a Ufer ground, is inspected far earlier, at the foundation stage, because it is buried in concrete.

The panel and the service

The service is the utility's connection to the house: the meter, the main disconnect and the conductors that feed the panel. Its size, stated in amperes on the panel label and the main breaker, sets how much load the house can carry, and it matters more each year as houses add electric vehicle chargers, heat pumps and induction ranges. Ask what the service size is and whether the panel has spare spaces for future circuits; both are easy to read off the label and hard to change later.

The panel is also where a new house's documentation lives. The circuit directory on the door should identify each breaker by what it serves, in words a stranger could follow. A directory filled in as "lights" and "plugs" is common and unhelpful, and the time to have it corrected is during the builder walk-through, while the electrician is still on the job. The panel door is also where the code requires the permanent energy certificate in most adoptions.

What the inspector looks for

Protection from fasteners. Cables run through holes in studs and joists. Where a hole is close to the edge of a framing member, a steel plate protects the cable from drywall screws and trim nails, the same principle as with pipes.

Support and routing. Cables are stapled within set distances of boxes and along their runs, not pulled tight across sharp edges, and not jammed against ducts or flues.

Box fill. Each box has a volume limit for the number and size of conductors and devices inside it. An overstuffed box overheats and makes later work dangerous.

Grounding and bonding. The equipment grounding conductors are connected, and the bonding of metal piping and CSST gas tubing is planned or in place.

What it does not establish

It does not test the circuits, which are not energized yet. Arc-fault (AFCI) and ground-fault (GFCI) protection are devices installed at the final stage; the rough inspection may confirm the circuit layout anticipates them, but the protection itself is checked when installed. It does not establish that the panel's circuit directory will be accurate, a frequent irritation in new houses.

What remains visible

After completion, the panel, its labeling, the breakers, the receptacles and switches, the smoke alarms and the service equipment are visible. A later inspection can test receptacles for polarity and ground, test GFCI and AFCI devices, and look inside the panel. The cables in the walls cannot be traced without opening the wall. The permanent energy certificate described at the energy code testing stage is often posted on or in this panel.

Common mistakes

Missing nail plates, overfilled boxes, cables run too close to the edge of a framing member, unsupported cable runs in attics, and bonding left for later and forgotten. In the finished house, the most common findings are mislabeled circuits, receptacles wired with reversed polarity, and GFCI protection missing in a location where it is required, such as a garage or exterior outlet.

Where the rules come from

The inspection sequence above is from Kingsville, Texas. The rule that rough inspections precede concealment is stated in local adoptions of the IRC such as the one indexed at ecode360.

Frequently Asked Questions

When is the electrical rough-in inspected?

After the wiring is run and before insulation and drywall cover it, at the same stage as the plumbing and mechanical rough-ins and before the framing inspection.

Are circuits tested at the rough-in?

No. The system is not energized at rough-in. Devices and protection are tested at the final.

What is a meter loop inspection?

The inspection of the service entrance and meter base that allows the utility to set the meter and provide permanent power.

What electrical items can a buyer check after move-in?

The panel and its labels, receptacles and switches, GFCI and AFCI devices, and smoke alarms. Wiring inside walls cannot be seen.