What this stage establishes
This stage establishes that the thermal envelope, the boundary between conditioned indoor space and the outdoors or unconditioned attic, was insulated and sealed as designed. Wall insulation goes into the stud cavities after the rough-ins and the framing inspection pass, and air sealing closes the gaps around wiring, plumbing and duct penetrations, top plates and the rim. Then drywall goes up and covers both.
Some jurisdictions inspect insulation separately; Groton, Connecticut, for example, lists an insulation inspection between framing and final. Many others rely on the blower door test at the end to reveal whether air sealing was done.
Installation quality matters as much as R-value
R-value is a material's resistance to heat flow; higher is better. But a batt rated R-13 performs well below that number if it is compressed behind wiring, left with gaps at the edges, or stuffed around a box instead of split around it. That is why insulation is judged by its installation, not just by its label. The common standard is that batts fill the cavity fully, touch all six sides, and are cut and fitted around obstructions.
Air sealing is separate from insulation. Insulation slows heat moving through materials. Air sealing stops air moving through gaps, carrying heat and moisture with it. A well-insulated house with leaky top plates and open penetrations into the attic will still lose much of its conditioned air. In a hot-humid climate, those leaks also pull moist attic air into the walls and living space.
Where the walls matter more than the attic
Attic insulation can be added or corrected after move-in at modest cost. Wall insulation cannot, short of opening the wall or drilling and blowing in fill. Air sealing at the top plates is reachable from the attic only before the attic insulation is blown in. That asymmetry is why the days before drywall matter: they are the only window to fix the expensive parts cheaply.
The attic details that decide performance
Because most Texas houses put the air handler and ducts in the attic, the attic floor is the main thermal boundary. Three details there are worth knowing. Baffles at the eaves keep blown insulation from blocking the soffit vents and keep the insulation from being blown back by air entering at the eaves. Depth markers, small rulers stapled to the trusses, show the installed depth of blown insulation so a buyer can confirm it later. And the attic hatch or pull-down stair is often the largest single uninsulated, unsealed opening in the ceiling; a weatherstripped, insulated cover is a small item with a measurable effect.
Spray foam applied to the underside of the roof deck changes the design: the attic becomes part of the conditioned space, and the ducts sit inside the thermal envelope. That is a legitimate approach with its own rules, and it changes the duct leakage limit that applies, as explained at energy code testing.
What gets hidden, and what stays
After completion, attic insulation remains visible and measurable by depth markers. Wall insulation and most air sealing are hidden. An infrared camera can reveal missing or compressed wall insulation as temperature patterns on the drywall, especially when there is a strong indoor-outdoor temperature difference, but it cannot reveal everything.
The energy certificate posted on or in the electrical panel records the insulation R-values the builder certifies for ceilings, walls and slab edges, along with window ratings and test results. It is described further at energy code testing.
Common mistakes
Gaps and compressed batts behind tubs and showers on exterior walls, empty cavities behind electrical panels, uninsulated walls between the garage and the house, unsealed top plates, and missing insulation in areas the attic blow-in does not reach, such as behind knee walls. Attic insulation blown in after the rough-ins but then disturbed by a later trade crawling through is common too.
Where the rules come from
The separate insulation inspection appears on lists such as Groton, Connecticut's required inspections. What the certificate must report is described in Washington's adopted R401.3 language.