What the final establishes
The final inspection establishes that the building department found the completed house compliant enough with the adopted code to be occupied. Under Section R110.1 of the International Residential Code (IRC), no building may be used or occupied until the building official issues a certificate of occupancy (CO). Under R110.3, the certificate states the building permit number, the address, the owner's name and address, a description of the portion of the structure it covers, the name of the building official, the edition of the code under which the permit was issued, and any special conditions of the permit.
That list is worth reading closely, because of what it does not include. A certificate of occupancy does not say the house is well built. It does not list defects. It records that the required inspections were completed and passed, and that the house may now be lived in.
What gets checked at final
The building final follows the trade finals for electrical, plumbing and mechanical. At the electrical final, the inspector checks devices, AFCI and GFCI protection, smoke alarms and the panel; at the plumbing final, fixtures, the water heater and its relief valve; at the mechanical final, the equipment and its connections. The building final itself covers items such as handrails and guards, stair dimensions, safety glazing, emergency escape openings, garage-to-house separation and the house number. In jurisdictions enforcing the energy code, the blower door and duct test results are part of it.
North Texas cities add paperwork. Dallas requires an energy code certificate before final. Lewisville and others require the termite protection affidavit before the final is scheduled by the builder.
Variations that matter to buyers
Some jurisdictions exempt one- and two-family houses from issuing a formal certificate but still prohibit occupancy until the building official releases the house after all required inspections pass. A temporary certificate of occupancy may allow move-in before minor items, often landscaping or a driveway, are finished, with a deadline to complete them. And outside city limits in Texas there may be no certificate at all; instead, the builder's three required inspections and the notice of them are the record. See new construction outside city limits.
What lenders do with it
Lenders treat the certificate as evidence the house was inspected. HUD's reference guide for FHA appraisals of new construction lists the building permit and certificate of occupancy, or the local equivalent, among the documents in the package. USDA Rural Development accepts a certificate of occupancy showing at least three construction-phase inspections, plus a one-year builder warranty, as one way to document inspections. See FHA and USDA new construction requirements.
Why a passed final is a floor, not a verdict
A building inspector reviews a finished house against code minimums, typically in a limited time and with a focus on life safety. Cosmetic and workmanship issues that meet no code requirement, many installation details hidden by earlier stages, and the performance of systems under real conditions are outside that scope. A passed final is the legal threshold for occupancy, which is important, and it is not the same as a finding that the house is free of defects. That is why many buyers also use the builder walk-through and an independent inspection before closing.
Getting a copy
Ask the builder for the certificate of occupancy at closing, and if it is not provided, request it and the inspection history from the city's permit office. Many cities publish permit records online by address. The certificate belongs at the front of the binder described in documents to collect at closing.
Where the rules come from
The model contents of a certificate are in the International Code Council's certificate of occupancy text and in adoptions such as Michigan's R110.3. Dallas's energy certificate rule is in its new construction requirements.