What final grading establishes
Final grading establishes that the ground around a new house slopes away from it, so rainwater runs off rather than collecting against the foundation. Section R401.3 of the International Residential Code (IRC) states the rule plainly: lots are graded to drain surface water away from foundation walls, and the grade falls a minimum of 6 inches within the first 10 feet. Where lot lines, walls, slopes or other barriers make that impossible, drains or swales must carry water away instead. Impervious surfaces within 10 feet of the foundation, such as patios, walks and driveways, slope at least 2 percent away from the building.
Six inches in ten feet is a 5 percent slope. It is the most checkable rule on this site: a buyer can verify it with a level, a string and a tape measure.
Why it matters more on slab houses in Texas
Much of North and Central Texas sits on expansive clay, soil that swells when wet and shrinks when dry. A slab on that soil moves when the moisture under it changes unevenly: one corner wet from a downspout and a flat yard, another dry under a sunny exposure. The Post-Tensioning Institute stresses that the long-term performance of a slab on ground depends on good drainage and on the owner maintaining it. Even a correctly designed and correctly stressed slab can crack and heave if water is allowed to pond along one side for years.
Nearly three-quarters of new single-family houses started in 2025 were built on slab foundations, according to NAHB's analysis of Census data, so this is the common case, not the exception.
Where the grade is set
The grade is shaped twice. Rough grade follows the foundation and sets the general shape of the lot. Final grade is cut near the end of construction, after utility trenches are backfilled and before sod and landscaping. The finish floor elevation set at the form survey limits what final grading can achieve: a slab placed too low relative to the street or the lots around it cannot be fully corrected with a rake.
Many subdivisions also have a lot drainage plan, prepared by the developer's engineer, showing which way each lot is meant to drain and where the swales run between houses. Ask for it. A swale that a neighbor's fence or flowerbed later blocks can send water toward your house.
The owner is the usual cause of failure
The builder sets the grade, and owners undo it. A raised flowerbed against the foundation, edging that traps water, a patio poured flat or sloping toward the house, mulch piled against the slab, or a fence built across a drainage swale can each reverse the slope. Bed soil also tends to rise above the slab edge, covering the brick veneer weep holes and the perimeter termite treatment zone described at termite pretreatment.
Gutters matter here too. Downspouts that discharge right at the foundation concentrate roof water exactly where the code says it should not collect. Extensions or splash blocks that carry it several feet out are cheap and effective.
How to check it
At several points around the house, lay a straight board or string from the foundation outward 10 feet, level it, and measure the drop from the level line to the ground at the 10-foot point. Six inches or more meets the code rule; less, or ground that rises away from the house, is worth raising with the builder during the warranty year. Watch the yard during a heavy rain: water standing within a few feet of the slab, or moving toward it, is the plainest evidence there is.
Common mistakes
Flat yards with no defined path for water, downspouts emptying at the slab, sidewalks that tilt toward the house, sod laid so its top sits above the slab edge, and drainage swales filled in during landscaping.
Where the rules come from
The drainage rule is quoted in the International Code Council's IRC Chapter 4 and explained in its rain and groundwater management note. The owner's role is stressed by the Post-Tensioning Institute.