New Build Checkpoints logo — a house frame with a checkmark at its peakNew Build CheckpointsWhat gets checked as a new house goes up
The paper trail

FHA and USDA new construction requirements: the inspections and warranty forms lenders need

Government-backed loans on new houses need proof the house was inspected during construction and a builder warranty, documented on specific forms.

The short answer

FHA-insured loans on new construction require the builder's Builder's Certification (form HUD-92541) and the Warranty of Completion of Construction (form HUD-92544), executed by the builder and the buyer, plus evidence of inspections such as the building permit and certificate of occupancy. USDA Rural Development guaranteed loans accept three ways to document inspections: a certificate of occupancy showing at least three construction-phase inspections plus a one-year builder warranty; three construction-phase inspections including the final plus a one-year warranty; or a final inspection plus a ten-year insured builder warranty. The lender handles the paperwork, but a buyer should know what exists and keep copies.

Why lenders care about construction inspections

A lender on an existing house relies on an appraisal of something that already exists and has a history. A lender on a new house is lending on construction that was just completed and largely hidden. The federal programs therefore ask for two kinds of assurance: that the house was inspected during construction, and that a builder stands behind it for a period after completion.

FHA: the two builder forms

Form HUD-92541, Builder's Certification of Plans, Specifications and Site. The builder answers a site analysis, including questions about hazards and adverse conditions, and certifies the plans and specifications. HUD's reference guide states that the certification must be signed and dated no more than 30 days before the appraisal was ordered for proposed, under-construction or less-than-one-year-old properties. Where the builder answers yes to certain site questions, engineering reports are attached.

Form HUD-92544, Warranty of Completion of Construction. The builder warrants construction in substantial conformity with the approved plans and specifications. FHA's Mortgagee Letter 2019-05 eliminated the old insured ten-year protection plan requirements and kept the HUD-92544 warranty as a condition of insurance, stating that it runs for one year from completion or occupancy, whichever comes first. Mortgagee Letter 2020-36 then made form HUD-92544 a requirement for all new construction.

HUD's guide also lists the building permit and certificate of occupancy, or the local equivalent, among the documents for a new-construction appraisal package. See final inspection and certificate of occupancy.

USDA: the three options

USDA's single-family guaranteed loan rules (7 CFR 3555.202(a) and Handbook HB-1-3555, Chapter 12.9 B) accept evidence of construction inspections in one of three forms:

  • a certificate of occupancy from the local jurisdiction showing it performed at least three construction-phase inspections, plus an acceptable one-year builder warranty;
  • three construction-phase inspections, including the final, plus a one-year builder warranty;
  • a final inspection plus a ten-year insured builder warranty.

These options matter most outside city limits, where there may be no certificate of occupancy and the inspections described in new construction outside city limits become the evidence a lender looks for.

VA and conventional loans

This page covers the two federal programs whose new-construction rules are most specific about inspection evidence. VA-guaranteed loans and conventional loans sold to Fannie Mae or Freddie Mac have their own requirements, which change over time and which the lender applies. The practical point is the same across programs: a lender on a brand-new house will want evidence of completion and inspection, usually the certificate of occupancy or its local equivalent, and sometimes a builder warranty. Ask your lender early which documents it will require, because a builder who learns of a requirement at the last minute can delay closing while the paper is assembled.

What a buyer should do with this

Ask the lender which documents it requires and request copies for your own files: the HUD-92544 warranty you signed, the HUD-92541 certification, and the inspection evidence. The HUD-92544 warranty and the builder's own warranty are separate documents with separate terms; read both. Put them with the rest of the paper described in documents to collect at closing. And note the dates: a one-year warranty that starts at completion may already be partly used when a buyer closes on a house that sat finished for months.

Where the rules come from

FHA's warranty requirement is in Mortgagee Letter 2019-05 and Mortgagee Letter 2020-36; the certification timing in HUD's reference guide. USDA's options are in its new construction training. Program rules change; confirm current requirements with the lender.

Frequently Asked Questions

What is form HUD-92544?

FHA's Warranty of Completion of Construction, executed by the builder and the buyer on new construction. It runs for one year from completion or occupancy, whichever comes first.

What is form HUD-92541?

The builder's certification of the plans, specifications and site, including a site hazard analysis, required for FHA new construction.

How many inspections does USDA require on a new house?

USDA accepts a certificate of occupancy showing at least three phase inspections plus a one-year warranty, three phase inspections including the final plus a one-year warranty, or a final inspection plus a ten-year insured warranty.

Does FHA still require a ten-year warranty?

No. Mortgagee Letter 2019-05 eliminated the insured ten-year protection plan requirement and kept the one-year HUD-92544 warranty.