Texas construction defect notice: how the Residential Construction Liability Act works

Before a Texas homeowner can sue a builder over a construction defect, the law requires written notice and a chance for the builder to inspect and offer a repair.

The short answer

Under Chapter 27 of the Texas Property Code, the Residential Construction Liability Act (RCLA), a homeowner seeking damages from a contractor for a construction defect must give the contractor written notice by certified mail, return receipt requested, describing the defects in reasonable detail, at least 60 days before filing suit or starting arbitration. The contractor may ask to inspect within 35 days of receiving the notice and may make a written offer of settlement, which can include an offer to repair, within 60 days. Rejecting a reasonable offer, or refusing a reasonable opportunity to inspect or repair, can limit what the homeowner later recovers. This page is general information, not legal advice; a construction defect claim warrants an attorney.

What the law is for

The RCLA's purpose is to encourage settlement before litigation by giving the builder a defined chance to see the problem and fix it. It applies to residences, including single-family houses, duplexes and triplexes. The Texas Residential Construction Commission, a state agency that once ran a separate inspection and dispute process for new homes, was abolished; in 2023, House Bill 2022 removed the statute's leftover references to that agency and updated the act, effective September 1, 2023.

The sequence

The statute sets the steps and the clocks:

  • Notice. At least 60 days before filing suit or initiating arbitration, the homeowner sends written notice by certified mail, return receipt requested, to the contractor's last known address, specifying the defects in reasonable detail.
  • Inspection. During the 35 days after receiving the notice, the contractor may, on written request, be given a reasonable opportunity to inspect the property and have it inspected, which can include photographs and testing.
  • Offer. Within 60 days after receiving the notice, the contractor may make a written settlement offer, which may be an offer to repair, an offer of money, or both. An offer to repair describes the repairs and the time to complete them.
  • Response and consequences. If the homeowner rejects a reasonable offer, or does not permit a reasonable opportunity to inspect or repair under an accepted offer, the damages the homeowner can recover are limited.

The statute also requires contractors to give homeowners a prescribed notice about these requirements in the contract, telling the buyer to send written notice by certified mail at least 60 days before filing suit and, if requested, to allow an opportunity to inspect and cure.

Why records decide these disputes

A defect notice is only as specific as the evidence behind it, and a contractor's inspection will look for alternative explanations. That is where the documents described in documents to collect at closing matter. A foundation complaint turns on the post-tension elongation record, the engineer's letters, and the history of drainage and grading around the house. A water intrusion complaint turns on what can be shown about the window flashing or brick drainage. Dated photographs, the signed walk-through punch list, warranty correspondence and any independent inspection reports establish when a problem was first observed and reported.

The relationship to the builder warranty

The RCLA does not replace the builder's written warranty. Most builder warranties have their own notice procedures and time limits, which run alongside the statute. Report problems under the warranty in writing as soon as they appear, keep copies, and note dates. A problem reported and documented during the first-year warranty is in a very different position than the same problem raised for the first time years later.

Where the law comes from

The act is Texas Property Code Chapter 27; the notice and offer rules are in §27.004; the 2023 amendments are summarized in the bill analysis of H.B. 2022. Read the current text before relying on any deadline here.

Frequently Asked Questions

How much notice must a Texas homeowner give a builder before suing over a defect?

Written notice by certified mail, return receipt requested, at least 60 days before filing suit or initiating arbitration, under Texas Property Code §27.004.

Does the builder get to inspect the defect?

Yes. On written request during the 35 days after receiving the notice, the contractor must be given a reasonable opportunity to inspect.

What happens if I refuse the builder's offer to repair?

If the offer was reasonable, refusing it can limit the damages you can later recover. An attorney can assess whether a particular offer is reasonable.

Does the RCLA replace the builder warranty?

No. The warranty's own notice requirements and time limits still apply and run alongside the statute.