The short answer
A useful new construction checklist is organized by when things get covered up, not by room. There are three moments that matter most: before the slab is poured, before drywall goes up, and before closing. At each one, a short list of items can be seen that will be hidden afterward, and a document can be requested that proves what happened. The lists below are a reference, not a substitute for a licensed inspector's report, and the items a given house needs depend on its design and its local code.
Stage one: before the pour
Everything below the slab is visible for a few days and then sealed for the life of the house.
- Location. Ask whether a form board survey was done and whether it shows the forms inside the setbacks and easements.
- Under-slab plumbing. The drain lines should be holding water for the test, with the standpipe charged; see under-slab plumbing.
- Vapor retarder. Continuous, lapped at seams, and patched where torn by foot traffic.
- Steel or tendons. Reinforcing steel supported off the ground on chairs; post-tension tendons supported and sheathing intact.
- Penetrations. Pipe sleeves and conduits where the plans put them.
- Termite treatment. Applied after trenching and before the vapor retarder; see termite pretreatment.
Documents to request: the foundation inspection result or the engineer's pre-pour letter, the form survey, and the termite treatment record. On a post-tensioned slab, ask that the elongation record be provided once the cables are stressed.
Stage two: before drywall
This is the most valuable inspection window in the whole build. The structure, every pipe and wire, the ducts, the window flashing and the insulation are all visible at once, for a week or less.
- Framing. Studs and joists not overcut by trades; connectors and hurricane ties where specified; trusses unaltered; see framing and bracing.
- Fireblocking. Penetrations through top plates and between floors closed.
- Plumbing and gas. Nail plates where pipes pass near framing edges; CSST bonded; see plumbing top-out.
- Electrical. Cables supported and protected, boxes not overfilled; see electrical rough-in.
- HVAC. Ducts supported without kinks, boots connected, bath fans ducted outdoors; see HVAC rough-in.
- Windows and wrap. Head flashing lapped under the house wrap above it, sill pans present; see windows and weather barrier.
- Insulation and air sealing. Batts filling cavities without gaps or compression, including behind tubs and on garage walls; top plates sealed; see insulation and air sealing.
Documents to request: the passed rough-in and framing inspection results, and, if the jurisdiction requires it, the HVAC load calculation and equipment selection.
Stage three: before closing
The finished house hides most of the above. What remains checkable is function, finish and drainage.
- Drainage. At least 6 inches of fall in the first 10 feet from the foundation; see final grading and drainage.
- Brick. Weep holes present, open and above the soil line; see brick veneer.
- Systems. Every fixture, appliance, heating and cooling function, GFCI and smoke alarm operates.
- Attic. Insulation depth markers, no daylight around roof penetrations, ducts connected.
- Energy certificate. Posted and filled in with tested results; see energy code testing.
- Punch list. Signed and dated; see builder walk-through.
Documents to request: the certificate of occupancy, warranty documents and registrations, appliance and equipment manuals, and the full set described in documents to collect at closing.
Why the timing beats the length of the list
A long checklist used once at closing finds paint and trim. A short checklist used at each cover-up point finds the expensive problems while they are cheap to fix. The guide to the cover-up point explains which defects are cheap before drywall and costly after.
Where the rules come from
The required code stages are listed in local adoptions such as Groton, Connecticut's required inspections. Texas law for houses outside city limits sets the same three key stages: foundation before concrete, framing and mechanical before drywall, and completion, in Local Government Code §233.154.